More Deliveries shortly

After a long wait, it seems that two more meaningful deliveries can be expected this month. Our trailing hornblocks are seen being machined, although there is still a lot to do. The main horn faces have to be machined, and eight bolt holes drilled in each face. As well as that Eagle Fabrications tell us that the cab splashers and associated parts will be ready this time next week.
Somers Forge are planning the forging of our connecting rods, so we will probably have a date for that very soon.
Finally, the right hand side coupling rod splasher will start production soon with the first step being the laser-cut steel plate profiles.
While we can expect limited progress in August as people take their holidays, after that we will have plenty to do with reaming out the hornblock holes and assembling the cab splashers into the outer cab panels.