Slide 1
Building a New Prince George Steam Locomotive

Welcome to the LNWR George the Fifth Project

previous arrowprevious arrow
next arrownext arrow
Slide 1
Building a New Prince George Steam Locomotive

Welcome to the LNWR George the Fifth Project

previous arrowprevious arrow
next arrownext arrow

Construction Timeline

2026-09-22

Frame Trial Fit of Hornblocks

Our Trailing hornblocks were delivered at last. We carried out a trial fit, and removed the Driving hornblocks to clean the interfaces. All were temporarily bolted up to achieve a nice snug fit.

Our

2026-09-22

2026-07-28

Cab Splashers Delivered

Eagle Fabrications have now delivered our cab splashers. 

We will fit them to our cab outer panels as soon as possible

2026-07-28

2026-02-04

Frame Assembly Milestone Achieved

Frame Assembly permanently fastened together, marking completion of our Frame Assembly Appeal.

2026-02-04

9 October 2025

Frame Assembly - Alignment of front frames, fitting buffer beam etc

Front frames now aligned, buffer beam fitted. It's looiking good!

9 October 2025

13 October 2025

Hornblocks Ordered

Hornblocks have been order from Trefoil Steel. Our Biggest order so far!

Driving Hornblock

Trailing Hornblock

 

13 October 2025

22 May 2025

First Stage Frame Assembly

First Stage Frame Assembly by Keyte Smith Ltd. Main Frame Plates, Dragbox, Motion Plate and Frame Stretcher now permanently assembled. A very significant step forward for the Trust!

22 May 2025

March 2025

Frames Prepared for Permanent Assembly

Everything stripped off the Main Frames ready for Permanent assembly.

Trial Fit of Front Frame Plates to Main Frames.

March 2025

March 2025

Front Frame Plates Delivered

Front Frame Plates now delivered, ready for assembly on to the main frame plateassembly.

Front Frame Plates Ready for Assembly

March 2025

February 2025

Motion Plate and Frame Stretcher Delivered

Boro Foundry have delivered our motion plate and frame stretcher. We plan to fit these by summer!

February 2025

December 2024

Dragbox Manufacture in Progress

Profile Cutting of dragbox plates is complete, and welding of the drawgear pivot housing “H” section is complete.

 

December 2024

November 2024

Motion Plate and Frame Stretcher Cast

Boro Foundry have cast our Motion Plate and Frame Stretcher. They now await machining when a slot is available.

Motion Plate and Frame Stretcher

November 2024

July 2024

Cab Footsteps Delivered, Acceptance Process Clarified

Cab footsteps have been delivered to Crewe Heritage Centre. They were fabricated by Metal World Engineering Limited. They have done a great job of imitating the look of the cast LNWR steps.

After delivery, we called in at Ricardo and discussed the submission for approval of the motion plate and frame stretcher. An intangible perhaps, but very important for our next steps.

July 2024

March 2024

Cab Upper Handrails

Keyte Smith, our long-term supporter, produced the top plate, tub and bottom boss. These were welded and polished by ACE Stainless Fabrications of Draycott near Derby. Their fabricated construction beautifully mimics the forged end of the original. Sadly, fitting these requires the cab top to be lifted, which is not possible at the Heritage Centre.

Cab Rear Handrails - Upper

March 2024

November 2023

Toolbox

Our Rusty LNWR Toolbox has been cleaned up, and put to use as a store for our tools and small parts at Crewe.

November 2023

July 2023

Crewe Heritage Centre

Our part-built replica of a 1910 LNWR ‘George the Fifth’ Class locomotive, by kind permission of the Palace carrying the number 2013 and named ‘Prince George’, has gone on public display at Crewe Heritage Centre.

The locomotive left the Kirkby-in Ashfield works of our contractor Keyte Smith Ltd. on a low loader and arrived at Crewe Heritage Centre a couple of hours later. It now forms the centrepiece of the Crewe Works area in the Main Hall, as part of the Forging History Exhibition celebrating the 180th anniversary of the establishment of Crewe Works, run in association with Crewe Town Council.

The LNWR built the original locomotives at the former number 9 Erecting Shop at the west end of the Works, now part of a housing estate.  The Trust is delighted to have the opportunity to display the locomotive at Crewe.  The Trust’s engineer is particularly pleased, having started his working life in Crewe Works in 1961.

On show, Crewe Heritage Centre

July 2023

December 2020

For the first time in 108 years two new George the Fifth main frame plates were set up

Main frame plates set up!

December 2020

December 2020

Main Frames Produced

December 2020

May 2020

Cab Construction Commences

May 2020

April 2019

No Longer Flatpack

Front end

April 2019

December 2018

Boiler Shell Design Underway

December 2018

October 2018

Handrail Complete

At last we have a welded handrail. As its a little over 6m long its a good job someone has a suitable boat trailer! Next job is to get it down to Hickling and hot work the two corners. Then a spray coat of black, mount the chimney and stand back to admire the view. Handrail fitted on 23rd October!

Handrail detail

October 2018

July 2018

Lamp Sockets Machined

Lamp socket work

July 2018

June 2018

Handrail Knobs Produced

Handrail Knobs

June 2018

May 2018

LNWR Loco Toolbox Obtained

We took possession of an LNWR loco toolbox (ex A E Grigg of Bletchley MPD) and LNWR design regulator and quadrant.

LNWR Loco Toolbox

May 2018

February 2018

Chimney and Capuchon Delivered

The base which fits onto the smokebox plus the stem of the chimney has now been mated with the top of the chimney.

Chimney, whistle and Team

February 2018

October 2017

Coupling Rods Forged

October 2017

Summer 2017

Chimney Top Cast

Chimney top graphic

Summer 2017

May 2016

Pattern for Bogie Wheels Complete

Bogie Wheel Pattern

May 2016

Spring 2016

Smokebox Complete

Initial painting

Spring 2016

June 2015

Front Buffer Beam Produced

June 2015

Autumn 2014

Front Frames Produced

Front frames which extend from the front buffer beam to just behind the motion.

Autumn 2014

July 2014

Prince George Unveiled

Twenty foot length of running plate of one side of the locomotive including splasher with nameplate and crest and lower cab side with numberplate all with authentic LNWR livery.

In a very smart move, and with permission, the locomotive is named Prince George, and has the number 2013, the year of the Prince’s birth. The first of the LNWR Class was of course named after the Prince’s great-great-great grandfather, King George the Fifth.

The Unveiling

July 2014

June 2012

Whistle - Donated by Robin Dean

Original item! It came from a tank engine which worked at Wolverton Works

Original Whistle

June 2012

Construction Timeline